Legal MacPac Home
Typical Installation Timeline
Back To Typical Schedule
Legal MacPac Task:
Firm or Department Task:
Task
Month One
Month Two
Month Three
Month Four
Customization - Version 1.0
Completed by LMP

5 weeks


Version 1.0 On-Site
Installation and Lab Test
1 day

Version 1.0 On-Site Pre-
Pilot Testing

1 week - Firm/Department submits Revision Notes at end of pre-pilot

Version 1.0 Revisions
Completed by LMP
1 week

Version 2.0 Installation
and Lab Testing
1 day

Task
Month One
Month Two
Month Three
Month Four
Version 2.0 On-Site
Pilot Testing

2 weeks - Firm/Department submits Revision Notes at end of pilot

Version 2.0 Revisions
Completed by LMP
1 week

Version 3.0 On-Site
Installation and Lab Testing
1 day

Version 3.0 On-Site
End-User Testing

2 weeks- Firm/Department submits Revision Notes at end of testing period

Version 3.0 Revisions
Completed by LMP

1 week

Version 4.0 On-Site
Installation and Lab Testing

1day

 

home ~MacPac 2000 ~ partnership program~ numbering 2000~ features ~ template list
typical schedule~ pricing ~ user's guide ~ design~ who we are ~ contact us ~ news

Copyright 1990-2008 The Sackett Group, Inc. All Rights Reserved.
For information about this site, contact info@legalmacpac.com

Legal MacPac